Public Works
2008 Road Program as of 9/12/08
- Peartree and Pensive Lanes are complete with the exception of the final wearing course of pavement.
- Pebble Lane has been reconstructed and concrete work has begun. Roughly one week to complete concrete; topsoil placement to commence upon concrete completion and driveway restoration upon concrete curing time (two weeks).
- Pond Lane will receive base pavement on Friday 9-12-08, concrete work to follow (two to three weeks time for completion of concrete) topsoil to commence upon concrete completion and driveway restoration upon concrete curing time (two weeks)
- Primrose Lane Storm sewer complete. Concrete curb to commence week of 15th. Road construction and concrete work will follow.
- Park Lane Storm sewer started Wednesday 9-10-08, curb to follow and two to three weeks. Road construction will follow.
- Post Lane Next road for construction. Work to begin two to three weeks.
- Pleasant and Butterfly Lanes scheduled for construction in November.
The following roads are scheduled to be done in the near future
- Berwyn Rd.
- Canterbury Rd.
- Peachtree Ln.
- Poplar Ln.
- Pin Ln.
- Port Ln.
- Poet Ln